The 33.70m high circular tank for cooling water storage has in internal diameter of 45.50 m, and was constructed using in-situ concreting operations. The 75 cm thick reinforced concrete wall is vertically reinforced by means of four pilaster strips - in the ring wall integrated buttresses, each 1.40m thick and 4.20m long.
Sunway Construction Sdn Bhd
For a project like this, the right choice of formwork system is tremendously important. We decided in favour of PERI because the systems are easy to use and ensure safe operational sequences. In connection with the PERI implementation planning and the construction site support, we can achieve fast cycle times.
PERI engineers designed a customised formwork solution comprising of VARIO Wall Formwork, CB240 climbing system and SK Tie system.