Sixth Avenue MRT Station
Downtown Line,
Singapore
Underground MRT Station
It connects the north-western and eastern regions of Singapore
Completion time: 2016
Location
Main Application
Civil Engineering
Project participants
Customer: McConnell Dowell SEA Pte Ltd
The Project
Impressions from the project process
MULTIPROP slab props enable the site to cast beams in a height of 5.10 m and 2.00 m thick slabs
The lightweight DOMINO panel formwork can be assembled with minimum crane assistance
SB brace frame and VARIO GT 24 wall formwork for casting of walls
ST 100 Stacking Towers are used for the construction of the station platform, concourse, and roof slab
MULTIPROP slab props enable the site to cast beams in a height of 5.10 m and 2.00 m thick slabs
The lightweight DOMINO panel formwork can be assembled with minimum crane assistance
SB brace frame and VARIO GT 24 wall formwork for casting of walls
ST 100 Stacking Towers are used for the construction of the station platform, concourse, and roof slab
Mr. Barry Mclean
Construction Manager
PERI has provided a professional service from the outset. Their VARIO and DOMINO systems are easy to use, flexible, and cost effective; they also improve the appearance of the site in terms of organization and housekeeping when compared to conventional formwork. The PERI design support has helped overcome potential problem areas that have helped maintain the progress of the project.