Pall Corporation Singapore Manufacturing Facility, Singapore
Benoi, Singapore
A&A works to existing 3-storey single-user industrial development.
Filtration solutions producer Pall Corporation is setting up a new manufacturing facility in Singapore which will support the semiconductor industry's needs in Asia-Pacific. The facility occupies a 2.8-hectare campus that will include more than 18,000 sqm of manufacturing and office space.
PERI supplied mainly shoring and column systems for this additions & alterations project.
The project commenced in Q1 2023 and is expected to be completed in Q3 2024.
Location
Main Application
Housing and Multi-Storey Buildings
Project participants
Main Contractor: Soilbuild Construction Group Ltd
Sub-contractor: Yizhan Construction Pte Ltd
Sub-contractor: Yizhan Construction Pte Ltd
The Project
Impressions from the project process
Pall Corporation SG Manufacturing Facility site progress: January 2023
Pall Corporation SG Manufacturing Facility site progress: February 2023
Additional columns casted for Production Block, preparing shoring for slab
Site crew assembling ST100 Stacking Tower with ease
PD8 frames and tabletops ready to be assembled
Pall Corporation SG Manufacturing Facility site progress: March 2023
First area of production block casted - approximately 1100sqm
2meters diagonal bracing was utilized to maximize the capacity of the PD8 frames
PERI Singapore Project Manager Edwin Ng and PERI Singapore Senior Product Specialist, Ah Chan in discussion of site progress
Pall Corporation SG Manufacturing Facility site progress: April 2023
A closer look at PD8 in use
Pall Corporation SG Manufacturing Facility site progress: June 2023
Utility Block consisting of 4 levels of slab
VARIO GT 24 Column Formwork complete with access ladders and pouring platforms
Mixed use of ST100 loosing shoring and PERI UP for 3rd level beams with maximum depth of 1400mm
Pall Corporation SG Manufacturing Facility site progress: January 2023
Pall Corporation SG Manufacturing Facility site progress: February 2023
Additional columns casted for Production Block, preparing shoring for slab
Site crew assembling ST100 Stacking Tower with ease
PD8 frames and tabletops ready to be assembled
Pall Corporation SG Manufacturing Facility site progress: March 2023
First area of production block casted - approximately 1100sqm
2meters diagonal bracing was utilized to maximize the capacity of the PD8 frames
PERI Singapore Project Manager Edwin Ng and PERI Singapore Senior Product Specialist, Ah Chan in discussion of site progress
Pall Corporation SG Manufacturing Facility site progress: April 2023
A closer look at PD8 in use
Pall Corporation SG Manufacturing Facility site progress: June 2023
Utility Block consisting of 4 levels of slab
VARIO GT 24 Column Formwork complete with access ladders and pouring platforms
Mixed use of ST100 loosing shoring and PERI UP for 3rd level beams with maximum depth of 1400mm