Sunview Logistics & Container Hub
Jurong,
Singapore
The new logistics facility is designed to support warehousing and container handling operations, with full operations targeted for 2027.
For these exceptionally tall 75-meter-tall columns, PERI Singapore supplied VARIO Formwork combined with CB Climbing Formwork, providing a functional and efficient solution for repeated casting and formwork repositioning, while providing a safe and practical working platform for the site team.
Beyond the columns, the same VARIO and CB systems were also utilised for the construction of multiple corewalls, providing a consistent formwork solution across the project.
PERI Singapore thanks Precise Development (Maincon) and Advanced Coretrades (Subcon) for the great partnership throughout the project.
Sub-contractor: Advanced Coretrades Pte Ltd
-
- A combination of VARIO + CB Climbing Formwork supplied to support the construction of 75 meter-high columns
-
- Over 100 columns per level casted
-
VARIO + CB Climbing Formwork was also utilized in the construction of corewalls
Overview of Sunview Logistics and Container Hub site in November 2025
Casting in progress for the required 74 meter-high corewall
Installation of precast beams
PERI Singapore supplied various sized VARIO GT24 Column Formwork throughout the site
VARIO GT24 Column Formwork System comes complete with safe and reliable working platforms
Columns casted efficiently with good progress
Site progress in January 2026
Site in near completion, September 2026
Overview of Sunview Logistics and Container Hub site in November 2025
Casting in progress for the required 74 meter-high corewall
Installation of precast beams
PERI Singapore supplied various sized VARIO GT24 Column Formwork throughout the site
VARIO GT24 Column Formwork System comes complete with safe and reliable working platforms
Columns casted efficiently with good progress
Site progress in January 2026
Site in near completion, September 2026