NSC N101 Viaduct, Singapore
Bayfront Avenue,
Singapore
PERI Singapore is proud to contribute to Contract N101 of the North–South Corridor (NSC), which includes the construction of elevated viaduct structures forming a key part of this major transport corridor. These viaducts are essential for improving traffic flow and supporting dedicated bus lanes along the alignment.
Our scope covered the construction of the viaduct pier heads. To deliver the works efficiently and safely, we deployed the RCS (Rail Climbing System) for systematic climbing operations, PERI UP Shoring Tower to provide stable and high load-bearing support, and DUO Panel Formwork as side formwork for its lightweight handling and flexibility on site.
We would like to thank our customer and main contractor, GS Engineering & Construction for the strong partnership and collaboration throughout this project.
-
- RCS as platform
-
- PERI UP Shoring and DUO Side Formwork to support the casting of viaduct pier heads
The NSC N101 package specifically covers works in the tunnel/viaduct section between ECP and Victoria Street
Sets of RCS platforms running parallel to Bayfront Avenue
A combination of three systems in play: RCS, PERI UP Shoring and DUO Side Formwork
Completion of pier head casting
The NSC N101 package specifically covers works in the tunnel/viaduct section between ECP and Victoria Street
Sets of RCS platforms running parallel to Bayfront Avenue
A combination of three systems in play: RCS, PERI UP Shoring and DUO Side Formwork
Completion of pier head casting