CB Climbing Formwork for corewalls + PERI UP MD (PS100 Shoring) for shoring

KWE Warehouse
Changi South Avenue 2, Singapore

Efficient Corewall Climbing at KWE Singapore Warehouse, Changi South.

Set for completion in 2027, the 4-storey KWE (KWE-Kintetsu World Express (S) Pte. Ltd.) warehouse in Changi South will expand KWE Singapore’s logistics and forwarding capabilities, increasing capacity and functionality to support its operations.

Working closely with Precise Development (main contractor) and Harvest Structure (subcontractor), PERI Singapore supplied climbing formwork solution for the construction of corewalls.

PERI’s CB Climbing Formwork enables the climbing unit and working platform to be lifted together as a complete unit, allowing the formwork to be repositioned efficiently between casting cycles. This supports faster climbing operations while providing a safe and practical working platform for the construction crew.

PERI Singapore thanks Precise Development and Harvest Structure for the valued collaboration on this project.

Main Application
Industrial Structures
Project participants
Sub-contractor: Harvest Structures Pte Ltd
Main Contractor: Precise Development
    • PERI UP MD (PS100 Shoring) provided for slab - shoring heights ranging from 5 to 7.3meters
    • GT24 Girder as primary and VT20 as secondary beams for shoring

PERI systems utilized

Find out more about the systems used in this project

CB Climbing Formwork for corewalls + PERI UP MD (PS100 Shoring) for shoring