50 meter-high columns required for Singapore’s Integrated Waste Management Facility project

Integrated Waste Management Facility IWMF
Tuas Nexus, Singapore

The IWMF (Integrated Waste Management Facility) is part of Singapore’s next-generation waste management infrastructure, designed to integrate multiple waste treatment processes into a single, highly efficient facility.

The project required precise vertical construction solutions for multiple high columns with varying heights, with the tallest exceeding 50 meters.

PERI Singapore supplied CB Climbing Formwork to support this challenging application. Using a controlled 6-meter casting cycle, the system enabled safe, efficient, and repeatable climbing progression throughout the works, ensuring stability and accuracy at every stage of construction.

Special thanks to Chian Teck Realty - project subcontractor and valued partner, for the collaboration and support throughout the execution of this project.

 

Location
Project participants
Sub-contractor: Chian Teck Realty Pte Ltd
    • CB Climbing Formwork for 50+ meter-high columns
    • CB Climbing Brackets allow for safe, rapid, and versatile vertical climbing