NUS E7

Project data

Location: Singapore, Singapore

NUS E7 is a unique facility that encompasses engineering and medical labs. It is located in the NUS (National University of Singapore) campus.

The facility serves clinicians, engineers, scientists and entrepreneurs to collectively gather to interact, discuss and collaboratively develop breakthrough medical technologies.

It will hold spaces such as state-of-the-art biomedical research labs, prototype labs, seminar rooms, a multi-purpose hall, an atrium galleria and a cafeteria.

Requirements

  • Slab and beam support throughout the facility
  • Shear walls within compound
  • Climbing formwork required for the building’s liftcore and staircase
  • Perimeter building protection for construction crew

Customer

Lian Soon Construction Pte Ltd

Customer's benefit

CB Climbing Formwork – Provides and ensures safe working conditions at all heights. The system can be adjusted quickly and easily with the use of crane.

PD 8 – Cost effective shoring system that can be quickly adapted to accomodate different heights for moving under large beams.

ST 100 Stacking Tower – Quick assembly, easy handling and minimal planning. With a single frame type, all required assembly height can be easily achieved.

PROKIT EP 110 – Secures open building edges, providing increased safe level of working areas and access ways of jobsite personnel.

DUO Universal Formwork – Simple handling and assembly due to the low weight and smart design of DUO’s system components. No extra tools needed.

PERI UP Flex – Highly flexible, adaptable and movable even in large units. PERI UP Flex also provides high level of safety with its self-securing deck and complete flat covering of working areas.

RCS Material Lifter – Providing flexibility as it can be variably positioned at any point of the building. Pre-assembled deliveries further enhances work efficiency.

Lim Sam Wan
Site Manager

PERI’s formwork instructors are knowledgable and experienced. They are always fast to help us whenever we encounter any technical difficulties on site. With that, construction progress went smoothly. We have greatly benefitted from this and we hope to work with PERI again.

PERI solution

  • CB Climbing Formwork used for the construction of the liftcores and staircases
  • PD 8 Shoring System, PERI UP Flex and ST 100 Stacking Towers enabled the casting of slabs and beams
  • PROKIT EP 110 increased level of edge protection around the perimeter
  • DUO Universal Formwork to construct shear walls throughout the facility
  • RCS Material Lifter used to lift tables to the next casting level in a short amount of time